πProject Highlights
The Quail Place Reconstruction Project includes the replacement of water mains, sanitary sewer mains and storm sewer infrastructure, as well as road widening and reconstruction.
π Key Project Dates
Preparations are underway, with construction expected to begin in the coming weeks on the Quail Place reconstruction project.
Project Start Date: March 27, 2026
Project Completion: June 30, 2026
Timelines can be impacted by weather, contractor performance, and other factors.
π Project Scope
π What work is being done?
- Water main installation
- Storm sewer catch basin & drywell installation
- Sanitary main installation
- Road widening and reconstruction
- Driveway repair
π§ What to Expect During Construction
Construction activities may result in occasional noise, dust, dirt, vibrations, and planned traffic interruptions. Work outside of typical construction hours may be required occasionally. Driveway access will be maintained within active construction zones on a daily basis, although there will be occasions where local traffic may not have access during working hours.
The Town of Osoyoos will have a comprehensive traffic management plan for this project that we will release to the public in advance of any traffic pattern changes.
π¦Ί Key Construction Activities:
Mobilization of crews, equipment, and materials to laydown areas
Direction drilling across the highway on 89th Street
Completion of all underground utilities
Completion of road reconstruction
Completion of asphalt installation
Demobilization of crews, equipment, and materials from construction site wide.
Please note that access for emergency vehicles will be maintained throughout the full project duration.