πProject Highlights
The 89th Street Reconstruction Project includes the replacement of water mains and storm sewer infrastructure, as well as full road reconstruction and the addition of a new multi-use pathway.
π Key Project Dates
Preparations are underway, with construction expected to begin in the coming weeks on the 89th Street reconstruction project.
Project Start Date: April 13th, 2026
Project Completion: August 21st, 2026
Timelines can be impacted by weather, contractor performance, and other factors.
π Project Scope
π What work is being done?
- underground utilities installation: water main, storm sewer, and sanitary sewer
- steel casing installation under the highway
- road reconstruction
- multi-use path construction
- concrete sidewalk
- Installation of lamp standards
ποΈ Phases of the Project
Phase One:
From intersection of 89th Street & 78th Avenue to 89th Street & 74a Avenue
π Timeline: April 13th - June 2nd

Phase Two:
From intersection of 89th Street & 70th Avenue to 89th Street & Kingfisher
π Timeline: May 7th - August 5th

Phase Three:
From intersection of 89th Street & 74a Avenue to 89th Street & 70 Avenue
π Timeline: June 25th - August 18th

π§ What to Expect During Construction
Construction activities may result in occasional noise, dust, dirt, vibrations, and planned traffic interruptions. Work outside of typical construction hours may be required occasionally. Driveway access will be maintained within active construction zones on a daily basis, although there will be occasions where local traffic may not have access during working hours.
The Town of Osoyoos will have a comprehensive traffic management plan for this project that we will release to the public in advance of any traffic pattern changes.
π¦Ί Key Construction Activities:
Mobilization of crews, equipment, and materials to laydown areas
Direction drilling across the highway on 89th Street
Completion of all underground utilities
Completion of road reconstruction
Completion of asphalt installation
Demobilization of crews, equipment, and materials from construction site wide.
Please note that access for emergency vehicles will be maintained throughout the full project duration.